| Project Component |
Spent to Date 03/31/10 |
Estimated Cost |
| Architectural design & services |
21,016 |
$20,000 |
| Engineering |
$21,403 |
$25,000 |
| Kitchen remodel |
$19,034 |
$25,000 |
| Power connections & supply |
$14,562 |
$20,000 |
| Septic systems |
$27,938 |
$50,000 |
| Fire road grading & gravel |
$12,012 |
$11,000 |
| Water system |
$142,621 |
$100,000 |
| Residence building construction |
$469,594 |
$670,000 |
| Retreat cabin construction |
$33,102 |
$75,000 |
5% Contingency/admin/
inviting generosity |
$38,017 |
$99,600 |
| Total |
$793,444 |
$1,095,600.00 |
|