Offerings Gathered:

Taking Delight in Giving
|
 |
| Project Component |
Spent to Date 12/06/08 |
Estimated Cost |
| Architectural design & services |
21,016.77 |
$20,000 |
| Engineering |
$20,031.19 |
$25,000 |
| Kitchen remodel |
$18,564.78 |
$25,000 |
| Power connections & supply |
$11,222.30 |
$20,000 |
| Septic systems |
$15,738.34 |
$50,000 |
| Fire road grading & gravel |
$12,012.27 |
$11,000 |
| Water system |
$142,091.45 |
$100,000 |
| Residence building construction |
$185,672.10 |
$670,000 |
| Retreat cabin construction |
$5,981.39 |
$75,000 |
9% Contingency/admin/
inviting generosity |
$4,294.00 |
$99,600 |
| Total |
$436,624.59 |
$1,095,600.00 |
|